A unique bike bridge connects the border of Slovakia and Hungary

Editor-in-Chief
20/11/2026

The construction of a cross-border pedestrian and bicycle bridge between the Slovak village of Dobrohošť (Dobrohošť) and the Hungarian Dunakiliti (Dunakiliti) has reached the final structural stage — builders are preparing to connect both parts of the structure over the old Danube riverbed. Although the opening of the facility has already been postponed twice, the first cyclists and pedestrians will be able to use the new route in 2027.

As reported by the state enterprise Vodohospodárska výstavba, the construction of the key section of the bridge is approaching an important engineering milestone. After long delays and resolving co-financing issues, work on the main crossing resumed in autumn 2025, and now engineers are preparing to join the shore and central sections of the structure.

What kind of bridge is this: technical features and architecture

The new crossing over the old Danube riverbed will connect the Dunajská Streda district (territory of the Small Žitný ostrov island in Slovakia) with the Hungarian Szigetköz region (Szigetköz). The structure will stand out with a recognizable silhouette featuring two tall pylons.

Characteristic

Indicator

Total length of the bridge

497.65 meters

Total width / roadway

4.9 m / 4 m (for pedestrians and cyclists)

Height of pylons (in the shape of the letter H)

43.27 m and 42.85 m

Number of cable stays

24 (arranged in two inclined planes)

Initial project budget (2023)

Over 10.4 million euros excluding VAT (50% — Slovakia, 50% — Hungary)

Structurally, the crossing consists of three parts: the Slovak left-bank section (110.2 m), the Hungarian right-bank section (137.2 m), and the central three-span cable-stayed bridge 250.25 meters long with a reinforced concrete deck.

Besides the bridge itself, the project includes the construction of access bike paths on both sides of the border:

  • On the Slovak side: a route 1,674 meters long will run from the small Dobrohošť hydroelectric power plant over a separate 64.8-meter bridge over the supply canal and further along the flood protection dam to the border.

  • On the Hungarian side: a 762-meter path will connect to the road leading over the Dunakiliti dam.

Convenient EuroVelo 6 routes and faster emergency rescue

The new bike bridge will be an important link connecting the Slovak and Hungarian parts of the popular international cycling route EuroVelo 6. This will open dozens of new cross-border routes for tourists and locals for bike rides and hikes along the picturesque Danube branches.

The project also has important practical significance for regional safety: the width and design of the bridge are calculated for the passage of emergency service vehicles and water management equipment. In case of emergencies in the border zone, ambulances and rescuers will be able to reach victims much faster.

When will the bridge open to visitors?

The idea of a bike crossing in this area has been discussed since 2008, and actual construction started in March 2023. According to the initial schedule, the bridge was planned to open in spring 2024, then the deadline was postponed to the end of 2026, but these dates were also missed.

Currently, the official date of the ceremonial opening has not yet been approved, as after joining the structure, builders will need time to complete finishing works and commission the facility. It is expected that the first cyclists and pedestrians will cross the new bridge in 2027.